Environmental Reports + Planning, Zoning & Development Documents: Danskammer
NYS Department of Public Service (Case Number:18-F-0325) and Danskammer Project Documents
tabbed table
Title |
Call # |
Pieces |
Site |
Notes |
e-Doc (if available) |
Public Involvement Program Plan
|
Dsk-1 |
1 |
|
July 2018 |
link
|
Filing of the Preliminary Scoping Statement
|
Dsk-2 2019 |
1
|
|
February 2019 NYSDPS case no. 18_F-0325
|
link
|
Preliminary Scoping Statement
|
Dsk-3 2019
|
1
|
|
February 2019 |
link
|
Visual Impact Assessment Progress Report
|
Dsk-4 2019
|
1
|
|
|
link
|
Filing of Danskammer Energy's Response to the Preliminary Scoping Statement Comments
|
Dsk-5 2019
|
1 |
|
April 2019
|
link
|
Proposed Stipulations Danskammer Energy Center
|
Dsk-6 2019
|
1
|
|
September 5, 2019
|
link
|
Application Cover Letter
|
Dsk-7 2019
|
1
|
|
December 11, 2019
|
link
|
DANSKAMMER ENERGY CENTER: APPLICATION FOR A CERTIFICATE OF ENVIRONMENTAL COMPATIBILITY AND PUBLIC NEED PERSUANT TO ARTICLE 10 OF THE NYS PUBLIC SERVICE LAW
|
Dsk-8 2019 Vol. 1
|
1 (inc flash drive) |
Danskammer
|
December 2019
|
|
DANSKAMMER ENERGY CENTER: APPLICATION FOR A CERTIFICATE OF ENVIRONMENTAL COMPATIBILITY AND PUBLIC NEED PERSUANT TO ARTICLE 10 OF THE NYS PUBLIC SERVICE LAW
|
Dsk-8 2019 Vol. 2
|
|
Danskammer
|
December 2019
|
|
DANSKAMMER ENERGY CENTER: APPLICATION FOR A CERTIFICATE OF ENVIRONMENTAL COMPATIBILITY AND PUBLIC NEED PERSUANT TO ARTICLE 10 OF THE NYS PUBLIC SERVICE LAW
|
Dsk-8 2019 Vol. 3
|
|
Danskammer
|
December 2019
|
|
DANSKAMMER ENERGY CENTER: APPLICATION FOR A CERTIFICATE OF ENVIRONMENTAL COMPATIBILITY AND PUBLIC NEED PERSUANT TO ARTICLE 10 OF THE NYS PUBLIC SERVICE LAW
|
Dsk-8 2019 Vol. 4
|
|
Danskammer
|
December 2019
|
|
Title |
Call # |
Pieces |
Notes |
Document |
DANSKAMMER ENERGY CENTER: APPLICATION FOR A CERTIFICATE OF ENVIRONMENTAL COMPATIBILITY AND PUBLIC NEED PERSUANT TO ARTICLE 10 OF THE NYS PUBLIC SERVICE LAW
|
Dsk-8 2019 Vol. 5
|
1
|
December 2019
|
|
DANSKAMMER ENERGY CENTER: APPLICATION FOR A CERTIFICATE OF ENVIRONMENTAL COMPATIBILITY AND PUBLIC NEED PERSUANT TO ARTICLE 10 OF THE NYS PUBLIC SERVICE LAW
|
Dsk-8 2019 Vol. 6
|
1
|
December 2019
|
|
DANSKAMMER ENERGY CENTER: APPLICATION FOR A CERTIFICATE OF ENVIRONMENTAL COMPATIBILITY AND PUBLIC NEED PERSUANT TO ARTICLE 10 OF THE NYS PUBLIC SERVICE LAW | Dsk-9 2019 |
1 | Attachemnts 1-3 December 11, 2019 |
|
DANSKAMMER ENERGY CENTER: APPLICATION FOR A CERTIFICATE OF ENVIRONMENTAL COMPATIBILITY AND PUBLIC NEED PERSUANT TO ARTICLE 10 OF THE NYS PUBLIC SERVICE LAW |
Dsk-10 |
1 | Lighting Analysis January 10, 2020 |
|
DANSKAMMER ENERGY CENTER: APPLICATION FOR A CERTIFICATE OF ENVIRONMENTAL COMPATIBILITY AND PUBLIC NEED PERSUANT TO ARTICLE 10 OF THE NYS PUBLIC SERVICE LAW | Dsk-11 2020 |
1 | Supplement to Application February 18, 2020 |
|
DANSKAMMER ENERGY CENTER: APPLICATION FOR A CERTIFICATE OF ENVIRONMENTAL COMPATIBILITY AND PUBLIC NEED PERSUANT TO ARTICLE 10 OF THE NYS PUBLIC SERVICE LAW | Dsk-12 2020 |
1 | March 2020 | |
Response to Notice of Incomplete Application: Title V Air Permit Application | Dsk-13 2020 |
1 | Response to Sept 2020 Deficiency Letter DEC ID: 3-3346-00011/00017 |
|
Response to Deficiency Letter Issued by NYSDPS on September 8, 2020 Case 18-F-0325 Danskammer Energy Center Application (Fourth Supplemental Filing to Article 10 Application) |
Dsk-14 2020 |
1 | Response to Sept 2020 Deficiency Letter |